Caltrans Logo

Eastbound I-580 HOV- Hacienda to Greenville

Description: In Alameda county on eastbound Route 580. Construct interim HOV between Hacienda Dr. and Greenville Overhead.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Alameda
City Dublin, Livermore, Pleasanton
Zip Code 94550, 94551, 94568, 94588
 
Senate District
09, 10
Assembly District 15, 18
Congressional District 10, 11
 
Caltrans District
04
 
 
County/State Route Alameda 580
Postmile Begin/End R  8.3 R  18.8
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  3522    3522  
Lane Miles Added (HOV)  10.9      
Peak Period Time Savings (minutes)  257080    257080  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Alameda County Transportation Commission Arthur L. Dao (510) 836-2560   adao@actia2022.com
Design (PS&E) Phase
Alameda County Transportation Commission Arthur L. Dao (510) 836-2560   adao@actia2022.com
Right of Way Phase
Alameda County Transportation Commission Arthur L. Dao (510) 836-2560   adao@actia2022.com
Construction Phase
Caltrans Cristna Ferraz (510) 286-3890   cristina_ferraz@dot.ca.gov
 
Corridor System Management Plan
Caltrans Juliana Gum (510) 286-4579   juliana_gum@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$0 $17,669 $17,669
CMIA
$72,200 $-17,859 $54,341
SHOPP Augmentation
$0 $31,694 $31,694
Non-bond Funding
State/Federal*
$69,669 $-54,669 $15,000
Local**
$12,000 $17,045 $29,045
Non Budgeted ETC
$0 $0 $0
 
Total**** $153,869 $-6,120 $147,749

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$12,000 $1,575 $13,575 $8,432
Design(PS&E)
$1,000 $1,570 $2,570 $1,051
Right of Way
$0 $400 $400 $3
Construction
$140,869 $-9,665 $131,204 $136,158
 
Total* $153,869 $-6,120 $147,749 $145,645

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
12/01/2001 

11/01/2007 
 

 
12/01/2001 

11/01/2007 
100  08/01/2002 

11/02/2007 
-8 

Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/01/2005 

02/01/2008 
 

 
03/01/2005 

06/01/2008 
100  03/01/2005 

06/19/2008 


-1 
Begin Right of Way Phase

End Right of Way Phase
11/01/2007 

02/01/2008 
 

 
11/01/2007 

02/01/2008 
100  12/01/2005 

02/28/2008 
23 

-1 
Begin Construction Phase

End Construction Phase
02/01/2009 

12/01/2011 
 

 
06/01/2008 

12/01/2011 
100  07/22/2009 

09/30/2011 
-14 

Begin Closeout Phase

End Closeout Phase
01/01/2012 

10/01/2012 
 

 
01/01/2012 

10/01/2012 
11/01/2011 

12/01/2013 


-14 
Corridor System Management Plan
Adoption Date     12/01/2009  100  05/01/2010  -5 
Implementation Date     12/01/2009  06/01/2010  -6 
????????
Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 3522 3522
Lane Miles Added (HOV) 10.9
Peak Period Time Savings (minutes) 257080 257080

Bond Funding Cost
Adopted:
$72,200,000
Current Approved:
$29,037,000
Actual Expenditures:
$28,891,000

 

Status as of December 31, 2023.